• English
  • Hindi
  • Punjabi
  • Marathi
  • German
  • Gujarati
  • Urdu
  • Telugu
  • Bengali
  • Kannada
  • Odia
  • Assamese
  • Nepali
  • Spanish
  • French
  • Japanese
  • Arabic
  • Home
  • Noida
  • National
    • BulletsIn
    • cliQ Explainer
    • Government Policy
    • New India
  • International
    • Middle East
    • Foreign
  • Entertainment
  • Business
    • Tender News
  • Sports
    • IPL2025
  • Services
    • Lifestyle
    • How To
    • Spiritual
      • Festival and Culture
    • Tech
Notification
  • Home
  • Noida
  • National
    • BulletsIn
    • cliQ Explainer
    • Government Policy
    • New India
  • International
    • Middle East
    • Foreign
  • Entertainment
  • Business
    • Tender News
  • Sports
    • IPL2025
  • Services
    • Lifestyle
    • How To
    • Spiritual
      • Festival and Culture
    • Tech
  • Home
  • Noida
  • National
    • BulletsIn
    • cliQ Explainer
    • Government Policy
    • New India
  • International
    • Middle East
    • Foreign
  • Entertainment
  • Business
    • Tender News
  • Sports
    • IPL2025
  • Services
    • Lifestyle
    • How To
    • Spiritual
      • Festival and Culture
    • Tech
  • Noida
  • National
  • International
  • Entertainment
  • Business
  • Sports
CliQ INDIA > Business > Telangana's Kaleshwaram irrigation project economically unviable, cost-benefit ratio inflated: CAG report
Business

Telangana's Kaleshwaram irrigation project economically unviable, cost-benefit ratio inflated: CAG report

cliQ India
cliQ India
Share
4 Min Read
SHARE

Hyderabad (Telangana) [India], February 17 (ANI):In what is a potential blow for the erstwhile K Chandrashekhar Rao-led BRS government in Telangana, a report of the Comptroller and Auditor General of India (CAG) revealed that the benefit-cost ratio (BCR) of the Kaleshwaram irrigation project was inflated, and the entire programme was economically unviable.

The cost of the Kaleshwaram project, which was initially estimated at Rs 81,911.01 crore, is now likely to exceed Rs 1,47,427.41 crore, with a cost overrun of about 80 per cent, the audit report tabled on Thursday said.

Even with the understated project cost of Rs 81,911.01 crore, benefit-cost ratio works out to be 0.75. Considering the latest likely project cost of Rs 1,47,427.41 crore, the BCR works out to 0.52.

“This means that every rupee spent on the project would yield only 52 paise. It clearly indicates that the project was, ab-initio, economically unviable,” the audit report stated.

“The Benefit-Cost Ratio (BCR) of the project was inflated by overstating the value of project benefits and understating the annual costs.”

The audit report into the big-ticket irrigation scheme revealed that the Government of Telangana did not accord administrative approval for the project, and instead issued separate approvals — as many as 73 administrative approvals aggregating to Rs 1,10,248.48 crore.

The audit report added that there were no orders from the government about the funding pattern for the project.

“The absence of a comprehensive plan duly spelling out the sources of funds for a project of this scale, which will have a long term impact on the finances of the State, is an indication of improper planning,” it said.

In 2008, the government of the erstwhile combined state of Andhra Pradesh took up the Dr B.R. Ambedkar Pranahitha-Chevella Sujala Sravanthi Lift Irrigation Scheme (PCSS Project) at a cost of Rs 38,500 crore.

The project proposed to lift 180 thousand million cubic feet (TMC) of water from Pranahitha and Godavari rivers and provide irrigation to a new command area of 16.40 lakh acres in the Telangana region.

Even without the approval of the project by the Central Water Commission (CWC), the project works were awarded to different contractors during 2008-2009 and execution of the works commenced.

After the state re-organisation in June 2014, the government of the newly formed state Telangana decided to re-engineer the project and divided it into two separate projects — the Dr. B.R. Ambedkar Pranahitha Project and the Kaleshwaram Project.

56 contracts were awarded under work for the Kaleshwaram project. The progress of project work is slow, the CAG report said.

“Out of the 56 works, only 12 works were completed, 40 works were ongoing with progress ranging from 3 per cent to 99 per cent while 4 works have not even commenced, as of March 2022. As against the total value of civil works of Rs 1,02,267.99 crore, the progress achieved was Rs 70,666.48 crore (i.e., 69 per cent),” the report read.

The delay in completion of works was mainly due to revisions in the scope of works and delays in finalisation of scope of works/designs/drawing and land acquisition, it argued. (ANI)

Click Here for more news: https://www.youtube.com/@cliQIndia

You Might Also Like

Centre Hikes MSP for 14 Kharif Crops, Paddy Price Raised Ahead of Monsoon Season | Cliq Latest
Indian markets open in green on global cues, US inflation shows a downward trend
Stock market soars in green: Sensex and Nifty rally in positive opening
China's DeepSeek sparks fear and AI price war, raises investor concerns: UBS Report
Japan SUNRISE TOURS New Veg Thali Meals by JTB Corp. on 1-Day Mt. Fuji and Hakone Tour for Indian Travellers

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Whatsapp Whatsapp Telegram Copy Link Print
Share
What do you think?
Love0
Sad0
Happy0
Angry0
Wink0
Previous Article ISL: In-form Mohun Bagan SG host upbeat Northeast United FC
Next Article "We will get PM Modi's roadmap and vision…" UP BJP Chief ahead of National Convention at Bharat Mandapam

Stay Connected

FacebookLike
XFollow
InstagramFollow
YoutubeSubscribe
TelegramFollow
- Advertisement -
Ad imageAd image

Latest News

Bengal Falta Repoll 2026: Massive Security Deployment After Election Controversy | Cliq Latest
National
May 21, 2026
Peddi Promotion Event In Bhopal: Ram Charan And AR Rahman Ready For Mega Show | Cliq Latest
Entertainment
May 21, 2026
Junior NTR Dragon Teaser Out: NTR Stuns Fans With Intense Assassin Avatar | Cliq Latest
Entertainment
May 21, 2026
KKR Vs MI IPL 2026: Manish Pandey And Bowlers Revive Kolkata Playoff Dream | Cliq Latest
Sports
May 21, 2026

//

We are rapidly growing digital news startup that is dedicated to providing reliable, unbiased, and real-time news to our audience.

We are rapidly growing digital news startup that is dedicated to providing reliable, unbiased, and real-time news to our audience.

Sign Up for Our Newsletter

Sign Up for Our Newsletter

Subscribe to our newsletter to get our newest articles instantly!

Follow US

Follow US

© 2026 cliQ India. All Rights Reserved.

CliQ INDIA
  • English – अंग्रेज़ी
  • Hindi – हिंदी
  • Punjabi – ਪੰਜਾਬੀ
  • Marathi – मराठी
  • German – Deutsch
  • Gujarati – ગુજરાતી
  • Urdu – اردو
  • Telugu – తెలుగు
  • Bengali – বাংলা
  • Kannada – ಕನ್ನಡ
  • Odia – ଓଡିଆ
  • Assamese – অসমীয়া
  • Nepali – नेपाली
  • Spanish – Española
  • French – Français
  • Japanese – フランス語
  • Arabic – فرنسي
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?